Road to Happiness: Work Progress for Phase II Part B

4/7/23

Work progress for II Phase building (Hostel Block).
二期 B大楼(宿舍楼)工程进展。
Internal wall putty works- 90% ongoing
内墙補泥工程- 90%进行中
Electrical works Internal wiring -100% Completed
电气工程内部电线-100%完成
Toilet wall tiles and floor tiles-100% completed
卫生间墙砖/地砖-100%完成
Kitchen table top – 100% completed
厨房桌面 – 100% 完成
Roofing works-100% completed
屋顶工程-100%完成
Septic tank works- 100% completed
化粪池工程- 100%完成
Septic tank sewage line to septic tank both the building -100% completed
化粪池污水管道至化粪池建筑物 -100% 完成
Staircase flooring works-100% completed
楼梯地板工程 -100% 完成
Bhutanese painting -40% completed
油漆-40%进行中
External painting – 100% completed
外部喷漆 – 100% 完成
False ceiling works- 60% ongoing
天花板工程 – 60% 进行中
Boundary wall fencing:
边界墙围栏:边界墙完成
No. of labours at site:
Mason workers-3nos (wall putty) Helper-2nos (wall putty) Carpenters- 4 nos
Electrical worker-2
Bhutanese painter-5 Total-16nos
现场劳动力人数:
泥工 – 3 名
助手 – 2 名
木工 – 4 名
电工- 2名
油漆工 -5名
共16名
只有感恩一切。